Tripoli Way May project update

21 May 2025

Early works including trenching and installing electrical conduits and electrical pillars commenced in March and progressed throughout May.

In total, 10,800 metres of conduit will be installed, which is currently over 80% completed. This will make way for new utility cabling, with Telstra and Optus on site to update networks in June and July.

For more details, view the full PDF here.

Hear from Executive Director of Infrastructure Services, Ben Stewart with the May project update.